Choice of Countermeasures in Project Risk Management Using Fuzzy Modelling
Keywords:
project risk, risk mitigation, risk transfer, risk elimination, fuzzy logicbased optimisationAbstract
The paper proposes a new method for project risk management. It is
proposed how, after risk identification, the countermeasures for risk mitigation and
elimination can be selected, taking into account the cost and effort linked to them
as well as the weights assigned by the decision maker to risk attributes, such as
probability or consequences, and the values of those attributes. The risk attributes
and weights, as well as the maximal total risk and the maximal total effort of risk
mitigation accepted by the decision maker for the project are expressed as fuzzy
numbers, which in turn constitute models for linguistic expressions.
References
Courtot H. (1988), La gestion des risques dans les projets, Ed. Economica, Paris.
Camilieri E. (2011), Project Success: Critical Factors and Behaviours, Gower Publishing Company.
Liu X. (2001), Measuring the satisfaction of constraints in fuzzy linear programming, Fuzzy Sets and Systems, 122(2): 263-275. http://dx.doi.org/10.1016/S0165-0114(00)00114-7
Mandal S., Maiti J. (2013), Risk analysis using FMEA: Fuzzy similarity value and possibility theory based approach, Expert Systems with Applications, 41(7): 3527-3537. http://dx.doi.org/10.1016/j.eswa.2013.10.058
Meyer A., Zimmermann, H. (2011); Applications of fuzzy technology in business intelligence. International Journal of Computers Communications & Control, 6(3): 428-441.
Norman T.L. (2010), Risk Analysis and Security Countermeasure Selection, CRC Press.
Shang K., Hossen Z. (2013); Research Paper: Applying Fuzzy Logic to Risk Assessment and Decision-Making, Casualty Actuarial Society, Canadian Institute of Actuaries, Society of Actuaries, 1-59.
Skorupka D. (2012), Method of Construction Projects Risk Assessment, Lambert Academic Publishing.
Wang Y.-M., Chin K.-S., Poon G. K. K., Yang J.-B. (2009), Risk evaluation in failure mode using fuzzy weighted geometric mean, Expert Systems with Applications, 1195-1207.http://dx.doi.org/10.1016/j.eswa.2007.11.028
Zhang Y., Zhi-Ping P. (2013); An optimization method for selecting project risk response strategies, International Journal of Project Management, 32(3); 412-422.http://dx.doi.org/10.1016/j.ijproman.2013.06.006
Published
Issue
Section
License
ONLINE OPEN ACCES: Acces to full text of each article and each issue are allowed for free in respect of Attribution-NonCommercial 4.0 International (CC BY-NC 4.0.
You are free to:
-Share: copy and redistribute the material in any medium or format;
-Adapt: remix, transform, and build upon the material.
The licensor cannot revoke these freedoms as long as you follow the license terms.
DISCLAIMER: The author(s) of each article appearing in International Journal of Computers Communications & Control is/are solely responsible for the content thereof; the publication of an article shall not constitute or be deemed to constitute any representation by the Editors or Agora University Press that the data presented therein are original, correct or sufficient to support the conclusions reached or that the experiment design or methodology is adequate.